Project Management โ€” Assignments

Work each problem yourself first, then open the worked solution to check your thinking. This is where the course sticks.

๐Ÿ“ 4 problemsโœ๏ธ Worked solutions
Problem 1

Take a real project you're facing. Write its one-sentence definition of 'done and good', then break it into tasks no bigger than ~2 days each.

Show worked solution

Example: ‘Done = a 3-page portfolio site, live on my domain, with my 5 best projects and a working contact form.’ Then tasks: buy domain, pick template, write project blurbs (one per project), set up contact form, test on mobile, publish. Each is concrete and estimable. If any task still feels vague or huge, it's hiding a sub-project โ€” split it further.

Problem 2

Estimate that project two ways: your gut estimate, then a buffered estimate (add ~50%, more for anything you've never done). Which is closer to what similar things have actually taken you?

Show worked solution

The lesson lands when the buffered number feels uncomfortably long โ€” and matches reality better. Example: ‘Gut: one weekend. Buffered: ~3 weekends once I count writing the copy, fixing the mobile layout, and the contact form I've never set up.’ Nearly everyone's honest history matches the buffered figure, not the gut one. That gap is the planning fallacy.

Problem 3

List everything you might want in the project, then sort it MoSCoW (Must / Should / Could / Won't-now). What's on your explicit 'Won't do now' list?

Show worked solution

The 'Won't' list is the real test. Example: Must: 5 projects, contact form, mobile-friendly. Should: an about page. Could: a blog, animations. Won't now: custom design, a CMS, dark mode. Naming what you're deliberately NOT doing is what stops 'ooh I'll just add a blog' from quietly turning a weekend into a month.

Problem 4

For your project, write a 3-row risk log: the risk, an early warning sign, and your plan if it happens.

Show worked solution

Example rows: (1) I lose motivation halfway โ€” sign: I skip two planned sessions โ€” plan: publish an ugly v1 fast to lock in momentum. (2) The contact form breaks โ€” sign: test email doesn't arrive โ€” plan: fall back to a mailto link. (3) Scope creeps โ€” sign: I start redesigning โ€” plan: park it on the Won't list. Each 'surprise' becomes a rehearsed, manageable event.