LEAD RISK ASSESSMENT โ MERESIDE WATER, 2033 (summary) Properties in supply area: 1,400,000. Estimated properties with lead in any part of the service pipe: 218,000 (15.6%). โ Lead communication pipe only (company side): 31,000. Action: replace. Unambiguously beneficial. โ Lead supply pipe only (customer side): 94,000. Action: none available to the company. โ Lead on both sides: 93,000. Action: partial replacement only, unless the owner replaces simultaneously. Properties with lead and an occupier under 6 or pregnant (modelled): approximately 14,800. Properties with lead and privately rented: approximately 61,000 (28% of the lead stock, against 19% of the stock overall). Replacement rate, company side, 2019โ2033: 14,200. At current rate, time to clear the 31,000 "company only": 30 years.
Ninety-three thousand properties where the only thing I may do is the thing that made 2B Glenvarra Road worse.
How we know where the lead is
Imperfectly, and I want to be honest about it because the numbers above look more solid than they are.
We know our own records back to about 1985 with confidence, and before that from a mixture of plans, card indexes and the memory of three retired inspectors. We know what we find when we dig. We infer the rest from the age of the housing stock, which is a good predictor and not a certain one.
For the customer side we know almost nothing except by excavation or by asking. A supply pipe is buried under a path and comes up under a floor. There is no register of it anywhere in the world.
So the ninety-three thousand is a modelled figure with an uncertainty I would put at plus or minus fifteen per cent, and the only way to improve it is to dig up ninety-three thousand front paths.
The twenty-eight per cent
Sixty-one thousand of the lead properties are privately rented, against nineteen per cent of our stock overall.
That is not a coincidence. Lead supplies are in the oldest housing, and the oldest housing โ Victorian and inter-war terraces, and conversions of both โ is disproportionately rented.
So the sub-population most exposed to lead is also the sub-population least able to authorise its removal, because a tenant cannot lawfully instruct work on the landlord's pipework and cannot be required to pay for it, and a landlord has no duty to do it and no benefit from doing it.
Chapter Eight is one landlord's reply.
The fourteen thousand eight hundred
Properties where we model a child under six or a pregnant woman and lead in the supply.
Lead's effects are on neurological development, and they are not reversible, and the dose that matters is the one in the first few years. A micrograms-per-litre figure on an adult's kitchen tap is a water quality statistic. On a two-year-old's it is an irreversible exposure during the only window in which it does that particular harm.
Nothing in the regulatory regime distinguishes between those two taps. The standard is ten micrograms per litre at a consumer tap. There is no separate standard, no priority, no trigger, and no duty differentiated by who lives there.
I asked, in 2031, whether we could prioritise our replacement programme on the modelled under-six data. We can and we do. It is a company policy, adopted on my recommendation, and it has no regulatory status, and the next water quality manager can withdraw it.
Thirty years
At our current rate of fourteen thousand two hundred over fourteen years โ about a thousand a year โ clearing the thirty-one thousand "company side only" properties takes another thirty.
That is the easy category. The unambiguously beneficial one. The one with no boundary problem, no consent problem and no chemistry problem.
The ninety-three thousand has no completion date at all, because its completion depends on ninety-three thousand private decisions by ninety-three thousand owners, nine per cent of whom say yes when asked at the only moment it is cheap to say yes.