SCHEME APPROVAL โ NETHER BARROW STW, PHOSPHORUS REMOVAL (water company business plan, price review 2034โ39) Driver: Water Framework Directive / environmental improvement. Consent to be tightened from 2.0 mg/l to 0.25 mg/l annual mean. Solution: tertiary treatment โ ferric dosing, tertiary clarification and sand filtration. Capital cost ยฃ14.2m. Operating cost ยฃ310,000 per annum (chemicals, power, sludge). Additional embodied and operational carbon over 25-year asset life: approximately 2,900 tCOโe. Additional sludge: 1,100 tonnes per annum (wet), to be recycled to land. Delivery: design 2035, construction 2037โ39, commissioning 2039. Expected classification effect: phosphate Good by 2041. Customer bill impact across the company's region: approximately ยฃ1.40 per household per annum.
Fourteen point two million pounds, two thousand nine hundred tonnes of carbon, and more than a thousand tonnes of sludge a year, to move one element of one water body across one boundary in 2041.
And I support it.
Why I support it
Because fifty-eight per cent of the load is that pipe, and there is no other way to reach it, and the Cawe will not be in good ecological condition until it is reached.
The algae on the gravels in August are phosphate. The macrophyte community is still recovering and will not get to High while that load continues. This is not a classification problem; it is a real ecological constraint and the scheme is the right scheme.
I wrote the supporting case. I would write it again. Fourteen point two million pounds is a lot of money and one pound forty on a household bill is not.
And why I am uneasy about it anyway
Three things, and the third is the one that matters.
The carbon. Two thousand nine hundred tonnes to improve one element. That is a real environmental cost incurred to achieve an environmental improvement, and the regime that requires the improvement does not account for the cost. Nobody nets it off. There is no field for it.
The sludge. Over a thousand tonnes a year to land, which is a phosphorus pathway of its own if it is spread badly.
The sequencing. The scheme was approved in the price review that followed eight years of catchment work โ and if the catchment work had never happened, it would have been approved anyway, in exactly the same form, for exactly the same reason. The two point one million pounds did not influence the fourteen point two million pounds by a single pound.
The counterfactual that bothers me
Suppose the partnership's two point one million pounds had instead been added to the works scheme.
The scheme would have been sixteen point three million pounds instead of fourteen point two and would have delivered a slightly tighter consent. Phosphate would have gone Good in 2041 either way. The classification outcome would have been identical.
And the Cawe would have no fish community, Moderate invertebrates, Poor macrophytes and oxygen crashes in August.
So the two point one million pounds bought the entire ecological recovery of that reach and precisely nothing in the classification, and the fourteen point two million pounds will buy one class boundary and comparatively little else.
Both are worth doing. Only one of them is visible.
What the price review process asked for
Evidence of need: the phosphate failure. Evidence of what catchment work had already achieved: not requested.
I offered it anyway, in an annexe, because I had it. The annexe was not referred to in the determination and I do not say that as a criticism โ the determination was about whether a phosphorus removal scheme was needed at Nether Barrow, and it was, and the answer did not depend on what fourteen kilometres of riparian planting had done to the invertebrates.
The two processes do not need each other's information. That is the whole structure of this book: two entirely rational pipelines, neither of which can see what the other achieved.