VARIATION REQUESTED, 8 July 2030; REVISED PROGRAMME AGREED, 19 July 2030 Developer: additional eleven weeks' excavation and specialist lifting funded (+ยฃ42,000). Site to be released to groundworks no later than 30 August 2030. Authority (me): agreed, on the basis that the structure is fully recorded, sampled and lifted within the period.
Sixty-four days between finding it and releasing the ground, and I agreed the date.
I want that on the record in my own words rather than discovered by somebody reading the file: the deadline that governed the most important excavation of my career was agreed by me, in writing, three weeks after the thing was found, and I would agree it again.
Why I agreed
Because the alternative was not an open-ended excavation. It was an argument I would lose, slowly, while the timbers dried out.
Waterlogged wood is only preserved while it is wet. Open the ground and you start a clock that runs in weeks: the structure that has survived three and a half thousand years begins to degrade the day it is exposed, and keeping a site wet through a summer requires pumps, sheeting and money, all of which the developer was paying for.
Had I refused the date and pushed for a stop, the developer's route was an appeal or a judicial review of my advice, which takes months. During those months the timber would have been under sheeting on a site with no contractor on it. I have seen a waterlogged structure lost that way, in 2018, during a dispute about who should pay to keep the pumps running.
So the choice was sixty-four properly funded days or an indefinite period of decay under a tarpaulin while lawyers corresponded. I took the sixty-four days and the extra forty-two thousand pounds.
What the eleven weeks were spent on
Worth setting out, because "an eleven-week extension" sounds like time to think and was not.
Two weeks de-watering and establishing a pumped sump so the trench could be worked without the structure floating. Three weeks cleaning, planning and photogrammetry โ every timber drawn at 1:10 in plan and the whole surface modelled twice, before and after the upper members were lifted. Two weeks lifting the 23 retained pieces, which is slow work: a waterlogged oak plank has the structural strength of wet cardboard and has to be supported along its length as it comes up.
Two weeks on the sequence beside the platform โ the samples that are now the unprocessed insect and pollen evidence. Two weeks recording and reburying the 191 timbers not retained.
Nobody sat down. The site ran six days a week through July and August with a crew of fourteen, and the director worked out on the last Friday that she had four hours of daylight left on the structure and spent them photographing joints.
What sixty-four days bought
A good excavation. I have read the site archive and it is careful work: every timber planned at 1:10, photogrammetric survey of the whole structure, 214 samples, the sequence recorded in section, lifting done properly by two conservators.
The record of that structure is, as a physical description, excellent. Nothing was rushed into a skip. Vanbrugh did what they were paid to do and slightly more.
And what the sixty-four days determined
That the only version of this structure that will ever exist is the one recorded between 27 June and 30 August 2030, by fourteen people, under a deadline, before anybody knew what questions it would raise.
You cannot go back. That is the whole meaning of preservation by record, and it is the sentence I write into every condition, and standing on the edge of that trench on a Thursday in August watching a mini-digger wait at the fence was the first time I properly understood what I had been writing.