SYSTEM STUDY — CALDERBECK 33 kV, 2030 (extract) Existing firm capacity at Calderbeck GSP group: fully allocated to connection agreements held by prior-dated applicants. Calderbeck Battery (49.9 MW) is therefore assessed against a network background including all prior-dated agreements as though energised. Result: export at 49.9 MW breaches the Scarrow–Netheridge boundary limit under N-1. Reinforcement required: Scarrow–Netheridge 400 kV circuit. Programmed energisation September 2042. Note: assessed without prior-dated agreements, Calderbeck connects at existing capacity with no reinforcement.
Two lines of the same study. With the queue ahead of it, Calderbeck needs seven hundred and forty million pounds of transmission. Without it, Calderbeck needs a switchgear bay and sixteen weeks.
Why the queue is not a waiting list
This is the part that almost nobody outside the industry understands, and it is the reason the queue cannot simply be shuffled.
A waiting list is a sequence of people who all want the same identical thing. The tenth person gets what the first person got, later.
A connection queue is not that. When I study your application, I must assume that everything ahead of you in the queue is built and running, because I am not allowed to assume otherwise — those are signed agreements and the network owes them capacity. So the network you are being connected to is not the network that exists. It is the network that would exist if every prior agreement were honoured, and your reinforcement requirement, your cost and your date all come out of that hypothetical machine.
Which means queue position does not determine when you are dealt with. It determines what you need.
The consequence
Harnforth did not apply too late for the capacity at Calderbeck. They applied too late for a network. The eight point six gigawatts of prior agreements I believe will never be built are, in every study I run, fully built — and they have consumed the boundary capacity, and the only way to get more boundary capacity is a 400 kV circuit, and that circuit is twelve years out.
I want to be exact: the capacity those projects hold is not idle. It has been spent. It is spent in my model the moment I run a study, and the result of spending it is a seven-hundred-and-forty-million-pound requirement charged, in part, to the people behind them.
And why reordering is not free
If I moved Calderbeck up, every study behind it would be wrong. Not out of date — wrong, because the network background each of them was assessed against would have changed, and their reinforcement requirements and their costs and their dates would all move.
There are two hundred and sixty-four agreements in my region. A reordering is a re-study of everything downstream of the change, each one taking weeks, each one producing a revised offer that the holder can accept or reject or modify, which changes the background again.
The queue is not a line of people. It is a chain of calculations, each one standing on the one in front of it. That is why "just move the real ones up" is an engineering statement about re-doing several years of work, not an administrative statement about a spreadsheet.