INTERNAL NOTE โ NOT ISSUED (H. MARRICK, AUGUST 2033) Review of 174 connection agreements prior-dated to Calderbeck Battery at the ScarrowโNetheridge boundary, against publicly available information only. No planning application traceable, 3+ years after connection application: 58. No substantive correspondence with the company in 24 months: 26. Land option or lease recorded as lapsed or site sold to an unrelated party: 9. Distinct agreements meeting at least one marker: 71 โ totalling 8.6 GW. Status: prepared on own initiative. Not a company position. Not acted upon.
I did this on a Sunday on my own laptop with a public planning portal and Companies House, and it is the single most useful document I have produced in fourteen years, and it has no standing whatsoever.
What the markers are and are not
They are not proof. I want to be harder on my own analysis than anybody else will be.
No planning application after three years is a strong marker and not a conclusive one. Some projects legitimately sequence consent after grid certainty, particularly where the planning route is a national one. I would guess that is a handful of the fifty-eight. I cannot tell you which.
No correspondence in twenty-four months is weaker than it sounds. A holder with nothing to do has nothing to write about, and my own process does not require them to write.
A lapsed land option is the strongest of the three and the rarest, because it is the one that is close to dispositive: you cannot build a battery on a field you have no rights to. Nine of them. Two had been sold for housing.
Overlap is heavy. Fifty-eight plus twenty-six plus nine is ninety-three, and the distinct count is seventy-one, which tells you that the projects with no planning application are largely the same ones that have gone quiet.
Eight point six gigawatts
Against a regional peak demand of two point one gigawatts.
I am aware that an enormous queue relative to demand is not in itself evidence of anything โ export projects do not serve local demand, and a region can and should host generation far in excess of what it uses. The comparison is not the argument.
The argument is the seventy-one. Eight point six gigawatts of boundary capacity, held by projects I can find no external evidence of, consumed in full in every study I run, generating a seven-hundred-and-forty-million-pound reinforcement requirement for the people behind them.
Why the note was never issued
Three reasons, in ascending order of how much they bother me.
It is not my job and nobody asked. I would have been presenting an unsolicited analysis of other companies' projects based on information I was not given by them.
It is legally awkward. "I have reviewed your competitors' land options in my own time" is a sentence that ends with a letter from a solicitor, and the company would have been right to be nervous.
And the third: it would have changed nothing, because there is no action it could have triggered. There is no provision in the methodology under which a lapsed land option, or a missing planning application, or two years of silence, does anything at all. The note describes a situation nobody has the power to respond to.
So it sat in a folder called queue on a laptop in Netheridge for three years, and the seventy-one are, as of this morning, seventy-four.