ENNERLY LOOP REFRESHERS โ SCHEDULED AND DELIVERED (R. L. FRAYNE, COMPETENCE RECORD) 2031: scheduled 48, delivered 29. 2032: 48 / 33. 2033: 48 / 30. 2034: 48 / 31. Deferred: 69. Refused: 0. Every deferral released a driver to cover a booked passenger service. Of the 69: 60 re-scheduled and delivered inside the 26-week window. 9 were not, and each of those nine was a lapse, reversible only by re-learning โ 8 return trips, about 19 hours of instructor time. Cadre movement 2030โ2035: 24 โ 17 + 12 = 19. The 17: nine deferral lapses, two retirements, one driver left the industry, one promotion (which I signed), one long-term sickness, one transfer, two depot moves. The 12 replacements cost 228 hours of driver-instructor time against six instructors who also deliver initial training, traction conversions and annual assessments. Nobody said no to anything. The register went from 24 to 19 out of a sequence of yeses.
Sixty-nine deferrals and not one refusal. I have checked that, because it surprised me.
How a deferral happens
On a Tuesday in February, Resource Control is four drivers short for the Wednesday. They look at what is booked that is not a passenger train, and one of the things booked is a driver going out on a loop refresher with an instructor.
So the refresher moves. It moves to a date inside the twenty-six weeks, which is correct and is what the standard contemplates, and the driver covers a service that would otherwise be cancelled.
That is not a failure of the system. That is the system working exactly as it should, because a cancelled train today is a definite harm to four hundred people and a deferred refresher is a contingent harm to nobody in particular.
I would make the same call. I have made the same call, as the person scheduling, when Resource Control asked nicely.
And then nine times it did not come back
Sixty of the sixty-nine were re-scheduled and delivered. That is a better recovery rate than I expected and it is a credit to the two planners who do it.
Nine were not, because the re-scheduled date was itself deferred, and the second date ran past the twenty-sixth week, and at the twenty-sixth week nothing dramatic happens. A field in a database changes colour.
No alarm sounds. No report is generated. The driver is not told, because he does not need to be told โ he is not booked on the route and will not be. And the cost of that colour change is nineteen hours of instructor time to reverse, which I have to find from six instructors who are the same six people who deliver every traction conversion and every annual assessment in the company.
The replacement problem is the real one
I put twelve drivers back on the register between 2030 and 2035. Two hundred and twenty-eight hours of cab time.
Each of those twelve is now a name that will itself lapse in twenty-six weeks unless a ride happens, and the rides are the thing that gets deferred.
So the register is a bucket with a hole in it and the only tap is the most oversubscribed resource in the company. Twelve in, seventeen out, over five years, with every individual decision correct โ and the thing I keep coming back to is that until the 23:42 stopped running in December 2028, the bucket had no hole in it, and nobody had ever had to find an hour of instructor time for the Ennerly loop at all.