MY SCHEDULE OF THE GAP — appended to my report of 7 June 2035 2011 assessment, as index-linked to the date of loss: £278,000. General construction inflation beyond the index: +£97,000. Current building regulations — fire compartmentation between bays, insulation to current standards: +£42,000. Licensed removal and disposal of asbestos cement roof sheeting: +£31,000. Rural access, scaffold, temporary roof and welfare: +£18,000. Floor area understated in the 2011 assessment by 41 m²: +£10,000. Total: the 2011 figure plus the five lines above is £410,000, which is my assessment of the full cost of reinstatement at 19 February 2035.
Five lines. Four of them are nobody's doing at all and the fifth is a surveyor's tape in 2011.
Ninety-seven thousand pounds of inflation beyond the index
This is the largest line and the least interesting, and it is simply what happened to construction costs between 2011 and 2035 for this kind of work in this kind of place, against a national all-sectors basket. Steel, labour, and the collapse in the number of firms willing to come out to a village for a job worth under half a million.
Forty-two thousand pounds of building regulations
You cannot rebuild a 1963 building to 1963 standards. Reinstatement means putting it back so that it can be used, and a workshop rebuilt today needs compartmentation between bays and insulation to current standards.
The policy covers this — most commercial policies do, and this one has a clause for it in terms — so it is not a coverage gap. It is a cost that did not exist in the 2011 figure because in 2011 the regulations were different, and a reinstatement assessment is a snapshot of what the rules required on the day it was made.
Nobody re-does an assessment because Part B has changed. There is no mechanism by which anybody is told that their sum insured has become inadequate because of a statutory instrument.
Thirty-one thousand pounds of asbestos
The roof sheets were asbestos cement, which was ordinary building material in 1963 and is now a licensed removal operation with enclosures, air monitoring and consigned waste.
The fire damaged them, which converts them from a thing you leave alone into a thing that must be removed under licence by a contractor with a four-week lead time.
In 2011 the surveyor assessed the cost of replacing a roof. In 2035 I assessed the cost of removing a regulated material and then replacing a roof.
Eighteen thousand pounds of getting there
A single-track access, a yard that will not take a 44-tonne delivery, a temporary roof over bay 2 for fourteen weeks because you cannot leave an open slab through a Shropshire spring, and welfare facilities for eight men where there is no mains drainage.
Ten thousand pounds of tape
The 2011 assessment understates the floor area by forty-one square metres. I have remeasured it three times and I am confident.
It is the only error by any person in this entire file, it is worth five per cent of the gap, it was made by a chartered surveyor who is now retired, and if it had never happened the Heskeths would have been underinsured by £54,000 instead of £64,000.