TEMPORARY SPEED RESTRICTION โ NOTICE TO DRIVERS, 6 May 2031 Bridge SEM/142, Netherfold. Down and Up lines, 142 m 10 ch to 142 m 32 ch. Permissible speed reduced from 90 mph to 20 mph. Reason: structural assessment. Duration: until further notice.
THE SAME RESTRICTION, LIFTED โ 22 November 2032 Duration in force: 566 days. Repair, once the possession was granted: 52 hours.
Five hundred and sixty-six days of twenty miles an hour, to fix something that took two days and a bit.
The word in the notice is temporary. It is the technical term and it is accurate in the sense the industry means it: a restriction imposed for a reason that will one day be resolved, as opposed to a permanent speed limit.
It is not accurate in the sense anybody else means it, and nothing in the notice, the system, or any process I had access to required anybody to say when it would end.
Who I am
Marianne Loach. I am forty-three and I am a route structures engineer, which means about nine hundred bridges, culverts, retaining walls and viaducts on one route: examining them, assessing them, deciding what to do when one of them is not what it was, and bidding for the access to put it right.
I imposed the restriction at Netherfold on 6 May 2031 and I was right to. I then spent eighteen months trying to get it lifted, and everybody I dealt with in that eighteen months was also right, and the railway ran at twenty miles an hour over a river in Lancashire for a year and a half.
The two numbers
The repair cost four hundred and ten thousand pounds. The possession to do it โ fifty-two hours, with diversions and replacement buses โ cost two hundred and sixty thousand. Six hundred and seventy thousand pounds, all of it visible, all of it in a budget, all of it requiring somebody's signature.
The restriction cost, on the most defensible estimate I can make, somewhere between six and twelve million pounds of delay, and about forty-two passenger-years of other people's time.
Not one penny of that appears in any budget anywhere. There is no line in any plan I have ever seen that holds the cost of a speed restriction. It is distributed across hundreds of thousands of journeys, recovered through a compensation regime that moves money between companies, and recorded โ when it is recorded at all โ as delay minutes in a performance report that nobody compares to a repair cost.
So the thing that could be authorised was expensive and the thing that happened by default was free, and the free one cost somewhere between ten and eighteen times as much.
Why I am writing it down
Because the restriction came off and the file closed, and a closed file on this railway contains the repair, the cost, the possession and the sign-off, and contains nothing at all about the five hundred and sixty-six days.
There is no document anywhere that records what the waiting cost. If somebody in 2040 reads the Netherfold file they will find a bearing replacement delivered under budget by a competent team, which is true, and they will have no way of discovering that it was the second-cheapest way of handling that bridge by a factor of about eighteen.
So this is the missing page of the file. It is not a complaint about anybody. I have deliberately used real dates, real figures and the real sequence, and where I have had to estimate I have said so and given the hostile version as well as mine.
What I want is for the next engineer who writes until further notice on a notice to drivers to have to write a date next to it, and the rest of this is my reasons for thinking that is a smaller request than it sounds.