EMAIL โ ACCESS PLANNING, 15 September 2031 "Marianne โ I've been through the rest of 31/32 and there is nothing I can offer you for a 52-hour blockade. Everything from now to March is committed and the Easter and May slots next year are the signalling. The first clean opportunity is November 2032. I can hold you a provisional for the weekend of 19/20 November. If you need it sooner it's a displacement, which is a conversation above both of us. What's the risk if it waits?"
That last question is the fairest question anybody asked me in eighteen months and I gave it a bad answer.
What I answered
I said that the structure was demonstrated at 20 mph with margin, that the examiner had found no evidence of movement under load, that we would monitor it at increased frequency, and that it could wait.
Every clause of that is true. It is also an answer to the question is it safe to wait, and the question he asked was what is the risk if it waits โ and the risk of waiting includes eighteen more months of 20 mph, which I did not mention, because in my head that was not a risk, it was an inconvenience, and inconvenience was not what an access planner was asking a structures engineer about.
I have thought about that reply more than anything else in this file. He gave me an open door and I walked past it with a correct sentence.
Why "is it safe" is the only question that gets asked
Because that is the question the system is built to ask an engineer, and it is the right question to build a system around.
Everything in my profession's training, standards and culture is organised so that when an engineer says a thing is not safe, it stops, and nobody argues about money. That is a genuine achievement, it took a century and several disasters, and I would not trade a millimetre of it.
The cost of it is that the only register in which I am fluent is safety. When the answer is it is safe at 20 mph, the conversation ends, because I have answered in the register that stops conversations โ and the thing that is now happening, which is a very large and widely distributed cost, is in a register I was never asked to speak.
The provisional
I accepted the provisional for 19/20 November 2032 and told him I would look at displacement.
It was the right operational decision on the information I had, it was made in about forty seconds, and it is the moment the eighteen months became eighteen months.
What I should have written back
Four lines, which I have since drafted about a dozen times, always the same shape:
Safety: it can wait. Demonstrated at 20 mph with margin, no movement under load, monitoring increased.
Cost of waiting: fourteen months at 20 mph. Ninety-four trains a day, three and a half minutes each โ about nine thousand two hundred delay minutes every four weeks. Call it six hundred thousand pounds a period.
Repair: six hundred and seventy thousand all in.
So one period of restriction costs about what the repair costs, and we are proposing to run it for eighteen more.
Every number in that is one I had, or could have had in an afternoon. None of it is an engineering judgement; all of it is arithmetic. And had I sent it, the conversation that followed would not have been is it safe to wait โ it would have been somebody above both of us having to write down why we were doing it anyway, which is all I am asking for in Chapter Fifteen.