ROUTE STRUCTURES โ TEMPORARY SPEED RESTRICTIONS IN FORCE, 1 SEPTEMBER 2033 Structures on route: 906. Structures-related TSRs in force: 41. Age of restriction: under 6 months โ 14. 6 to 12 months โ 10. Over 12 months โ 17. Of which over 3 years โ 6. Oldest: BRX/088, imposed March 2026, seven years five months. Mean age of a structures TSR on this route: 14 months. Restrictions in force with a confirmed repair date: 9.
Forty-one restrictions. Nine of them have a date. Netherfold was one of the lucky ones.
BRX/088
A masonry arch near Brixworth Lane with a 30 mph restriction imposed in March 2026 for arch ring separation, monitored quarterly, no change recorded in seven years.
There is no plan to repair it. There is no plan not to repair it. It is not on a list of deferred work, because deferral implies an intention; it is simply the condition of that piece of railway, and every timetable written since December 2026 has had it built in.
Nobody made that decision. Three engineers have held my job since 2026 and each of them inherited BRX/088 as part of the furniture of the route, the way you inherit a gradient.
A restriction that outlives the people who imposed it has stopped being temporary in any sense except the word on the notice.
The number I made myself calculate
In August 2033 I took the forty-one restrictions and did for all of them what I had failed to do for Netherfold in 2031: train counts, running-time penalties, duration to date.
It came to roughly three hundred thousand delay minutes a year across the route. At the regime's figure that is around nineteen million pounds annually, and the honest part of that is that about two thirds of it is now built into the timetable, so it does not show up as delay anywhere โ it shows up as journey times being what they are.
I am not confident in that figure to better than about twenty per cent. I am completely confident that it is not small, and that it is larger than the entire structures renewals allocation for this route, which is nine point six million pounds a year.
The restrictions cost more than fixing the things they restrict. I would like to tell you this is a known fact that is being worked on. It is a calculation I did on my own initiative, in a spreadsheet, on my own laptop, and nobody above me has ever asked for it.
Why forty-one is not evidence of failure
Every one of the forty-one is defensible.
Each was imposed because a structure could not be demonstrated at line speed. Each is monitored. Each is held by somebody who would rather it were not there. Not one of them is a case of somebody taking the easy option out of laziness.
They have accumulated because imposing is free and immediate and in one person's gift, and removing requires money, a possession, a business case and a queue โ and a system where the brake is free and the repair is expensive will fill up with brakes, one correct decision at a time, until the brakes are the railway.