POST-EXCAVATION ASSESSMENT, 14 March 2031 (recommendations, extract) The waterlogged structure is of regional and probably national significance. The assemblage has high potential to address research aims 2, 4 and 7 of the regional framework. Recommended programme: dendrochronology (40 timbers); woodworking analysis; pollen, insect and plant macrofossil analysis of the associated sequence; radiocarbon (12); conservation (23 timbers); synthesis and publication in a regional or national journal. Estimated cost: ยฃ97,000. Estimated duration: 18 months.
That is a good assessment, honestly costed, and the number is not padded โ I have checked it against two other quotes since and it is if anything light on the conservation.
It was sent to the developer on 20 March 2031 and refused on 5 June 2031.
The refusal
Four paragraphs, courteous, from a project director I had dealt with for two years and liked.
It said that the company had met every obligation under condition 14; that it had funded an evaluation, an excavation, an eleven-week extension at an additional ยฃ42,000 and an assessment, totalling just over three hundred thousand pounds against an original budget of two hundred and twenty-seven; that the WSI provided for analysis to be the subject of a separate agreement; and that the company was not in a position to enter into one.
The final paragraph said that the scheme had been completed eight months previously, that the project accounts were closed, and that the development company itself โ a special purpose vehicle, as these always are โ would be wound up by the end of the year.
Every sentence in that letter is true and the last one is the important one.
What I said back
I replied on 11 June 2031, and I have the letter in front of me.
I set out what the assessment had found, what the analysis would cost, and what two tenths of one per cent of a forty-one million pound scheme comes to. I said the structure was the best of its kind recorded in the county. I asked them to reconsider, and I offered to approach the parent company myself if that was easier, and I offered to write to the trade press jointly if they funded it, which is the only inducement I have ever had to offer anybody.
I received a reply in nine days saying no, again courteously, and repeating that the accounts were closed.
I then telephoned the parent company's development director, which was outside anything my role requires, and he took the call, and he listened for about six minutes, and he said the thing that ended it: that he had no mechanism to spend money on a completed asset, that his board would ask what the company was buying, and that the honest answer was nothing.
He was not being cynical. He was describing how a company works. There is no line in any corporate budget for the analysis of something you have already destroyed with permission.
The special purpose vehicle
Large schemes are built by companies created for the scheme and dissolved after it. That is not evasion; it is ordinary project finance, it ring-fences risk, and it is how nearly every development of this size in this country is done.
It also means that the entity which incurred the archaeological obligation ceases to exist, usually within about a year of the ground being released. By the time an assessment tells you what the analysis should cost, there is frequently nobody left to ask.
I checked the register in December 2031. The company was dissolved on 14 November 2031, five months after the refusal and twenty-two months after the ground was released.
Nobody did anything improper. The condition had been discharged โ I discharged it myself in February 2032, on receipt of the grey literature report, because the condition as written required a programme of work in accordance with the approved WSI, and that is exactly what had been delivered.
I signed the discharge. There was no basis on which I could refuse it, and the file is closed.