MY NOTE TO THE PLANNING MANAGER, 9 June 2031 "The analysis has been declined. I have looked for a route and there is not one. Condition 14 required a programme in accordance with an approved WSI. The WSI made analysis subject to a separate agreement. No agreement has been made and none can be compelled. The condition has been complied with. If we refuse to discharge it we will lose, and we will have spent officer time establishing in public that our standard condition does not do what we say it does." Reply, same day: "Agreed. Discharge it."
That exchange took nine minutes and it is the most honest piece of paper in this file.
Why the condition does not reach
A planning condition must be enforceable, precise, and relevant to planning. Those are not bureaucratic hurdles; they are what stops conditions being used to extract things from applicants that have nothing to do with the development.
A condition requiring analysis and publication to a standard and scope to be determined later, at a cost not yet known, by an entity that may not exist fails on precision, and would be struck out on appeal in an afternoon. I know this because a neighbouring authority tried a version of it in 2027 and that is what happened, and the appeal decision is now cited at me by agents.
So the condition says what it can say: do a programme of work in accordance with an approved scheme. And the scheme, for the reasons in Chapter Four, cannot fix the analysis scope in advance.
The limits on what a condition may say and the impossibility of costing analysis before excavation are each entirely sound, and the gap between them is where the second half of every excavation falls.
The thing I tried
In 2028 I began writing briefs that required the WSI to include an indicative provision for post-excavation analysis of not less than 25% of the excavation cost, to be adjusted following assessment.
Three agents objected. One appealed a different condition and raised it in passing; the inspector observed, in a sentence I have memorised, that the requirement is not sufficiently precise to be enforceable and appears to seek a financial contribution by the back door.
He was right about the second part. That is exactly what it was, and a planning condition may not require a payment โ payments are secured by agreement, under a different mechanism, which is Chapter Fifteen and which nobody uses for archaeology.
I stopped including it in 2029, four months before I wrote the Barrow Heys brief.
What I think about my own note
We will have spent officer time establishing in public that our standard condition does not do what we say it does.
I wrote that as a practical argument to a manager and it is also a confession. The reason for the condition, printed on the permission, is to ensure that the archaeological interest is preserved by record. The condition secures the excavation. It does not secure the record in the sense that sentence means, and the profession knows it, and we go on printing the sentence because it is true of the part the condition does reach.