Chapter OneTwelve Years and Four Months

Chapter 1 of 183 min read691 words

CONNECTION OFFER โ€” HARNFORTH ENERGY LTD, CALDERBECK BATTERY STORAGE Application received: 14 March 2030. Capacity applied for: 49.9 MW (99.8 MWh). Point of connection: Calderbeck 33 kV substation, Bay 4. Earliest connection date: 1 October 2042. Reason: connection is dependent on completion of the Scarrowโ€“Netheridge 400 kV reinforcement, programmed for energisation September 2042. Annual cost to the applicant of holding this agreement: ยฃ14,000.

Twelve years and four months. That is not a delay and it is not an error; it is the correct answer, produced by a correct process, and I signed it.

โ–

The other number in that letter

Fourteen thousand pounds a year.

That is what it costs Harnforth Energy to hold the queue position which, in 2042, will give them a 49.9 MW battery. It is also what it costs anybody else to hold a queue position: a company with a signed land option and a planning consent and a bank, and a company with a spreadsheet and a company registration and no intention of building anything at all.

The scarcest thing in the British electricity system is a place in the connection queue, and it is one of the cheapest things in the British electricity system to hold.

โ–

Who I am

Hilary Marrick. I am fifty-one and I am connections planning manager for a regional distribution network, which means I am the person who receives an application to connect something to the grid, works out what the network would have to become in order to accept it, and writes back with a date and a price.

I have done that job for fourteen years. In 2019 a 49.9 MW application in my region would have been offered a date about nineteen months out. The letter above offers twelve years and four months, and everything between those two sentences is this book.

โ–

What I am not going to say

I am not going to tell you the queue is a scandal, or that anybody in it is a fraud, or that my industry is obstructive. I have read a great deal of that and almost none of it survives contact with the files.

Here is what I am going to say, and I am going to spend eighteen documents proving it.

The queue is ordered first come, first served. That is the only ordering rule available to me which is not arbitrary, which I can defend to every applicant, and which cannot be litigated โ€” and it is the only ordering rule which is completely incapable of telling the difference between a project that will be built and a project that will not.

The fairness and the failure are the same property. You cannot remove one without removing the other, and nobody involved has done anything wrong.

Of the one hundred and seventy-four projects ahead of Calderbeck in my region, I can show you seventy-one โ€” eight point six gigawatts of them โ€” that I believe will never be built. I cannot act on that belief. I am not permitted to, I have no standing to, and if I am honest I am not even certain I am right.

โ–

Why I am writing it down

Because the Calderbeck file closed in August 2030 and contains an application, a study, an offer, a termination at the customer's request, and nothing else.

A person reading it in 2040 will see a developer who asked for a connection, received a lawful offer, and chose not to take it. That is an accurate summary and it is also a description of nothing at all. The file does not record that the project needed no reinforcement, that the date came from somebody else's circuit, or that a battery was available for three years at a boundary where sixty-eight million pounds was paid last year to turn wind off.

So this is the part of the file nobody is required to keep. The dates, the capacities and the figures are real; where I have estimated I say so and give the hostile version too; and where my own analysis has no standing I say that first rather than last.