Books › Queue Position
Queue Position ยท a novel

Chapter TwoWhat a Connections Manager Does

Chapter 2 of 183 min read671 words

ROLE โ€” CONNECTIONS PLANNING MANAGER Receive and validate applications for connection to the distribution network; carry out or commission system studies to establish the point of connection, reinforcement requirement and earliest connection date; issue offers within the statutory period; maintain the register of connection agreements; manage the queue in accordance with the connection charging and queue management methodologies. Duty: to offer terms for a connection to any person who requests one.

That last line is the whole architecture. I do not choose who connects. I am obliged to offer terms to anybody who asks.

โ–

What the duty means

If you write to me tomorrow asking to connect a hundred megawatts of solar at a field outside Netheridge, I must study it and I must offer you terms. I may not ask whether you own the field. I may not ask whether you have money. I may not decline because I think your project is unserious, and I may not put you behind somebody I think is more serious.

That obligation is not an oversight. It is the thing that stops a monopoly network โ€” and I run a monopoly โ€” from deciding which businesses exist. Before it was imposed, network companies did decide, and they decided in favour of people they knew and against people they did not.

I would not give it up. I am describing a protection, not a loophole.

โ–

The three things I produce

A point of connection. Where on my network your thing can physically attach. This is engineering and it is not controversial.

A reinforcement requirement. What has to be built โ€” a new transformer, a new circuit, in the worst cases a transmission upgrade that is not even mine โ€” before the network can accept what you want to put on it or take off it.

A date. Which is the date the last piece of necessary reinforcement is finished. Not the date I could build your bay; the date the slowest thing you depend on is done.

Calderbeck's bay would take sixteen weeks. Calderbeck's date is 2042.

โ–

What I cannot do

I cannot create capacity. I cannot accelerate transmission reinforcement, which belongs to a different company under a different licence with its own queue and its own consenting process.

I cannot reorder the queue on my own judgement. Queue position is set by the date a valid application was received, and it is held in a register that is auditable, disclosable and โ€” this matters more than anything โ€” the same for everybody.

And I cannot ask an applicant to prove their project is real, because there is no provision anywhere in the methodology that lets me, and because the first time I tried it would be the last.

So I hold the pen on a document that decides which energy projects in this region happen, and the only input I am allowed to use is the order in which the post arrived.

โ–

The two clocks

The other thing to hold in your head is that I work to two calendars that do not speak to each other.

Mine runs in weeks: an application validated, a study commissioned, an offer issued inside the statutory period, a bay built in sixteen. I am good at that calendar and so is my team; we have never missed a statutory offer date in my fourteen years.

The calendar that actually decides everything runs in decades, and it belongs to somebody else: transmission reinforcement, consenting, price control periods. A development consent order is not a thing I can expedite, escalate or be told the progress of beyond what is published.

So I am a fast process bolted onto a slow one, and every date I issue is the slow one's date wearing my letterhead. Applicants are furious with me about dates I did not choose and cannot move, and I have stopped explaining that, because explaining it sounds like an excuse and because from where they are sitting the distinction makes no difference at all.

All 18 chapters · Queue Position

Use the ← and → arrow keys to turn the page. Your place is kept in this browser.