WHAT THE QUEUE COSTS — H. MARRICK, SEPTEMBER 2033 (own analysis, lower bounds) Constraint payments, Scarrow–Netheridge boundary, three years to March 2033: £186m. Reinforcement requirement attributable to the 8.6 GW of unverifiable agreements, as apportioned in offers issued since 2030: £214m of the £740m circuit. Projects abandoned after receiving a connection date beyond their financing horizon, 2030–33, this region: 17 (total 1.1 GW). Of those 17, number whose own project required no reinforcement when assessed in isolation: 6. Annual cost to the holders of the 8.6 GW of maintaining those agreements: about £2.6m.
Two point six million pounds a year of holding costs. On the other side of the ledger, numbers in the hundreds of millions. That is the ratio, and it is not close.
What is solid here and what is not
The constraint payments are published and they are exact; what is not exact is how much of them a battery at Calderbeck would have absorbed, and I have deliberately not claimed a figure.
The two hundred and fourteen million is an apportionment, taken from the way my own offers allocate reinforcement cost by contracted capacity, and it is defensible but it is arithmetic on a hypothetical. If the circuit is needed anyway — and Chapter Eleven says it probably is — then some of that money is not saved by anything I propose, and I am not going to pretend otherwise.
The number I stand behind completely is the seventeen.
The seventeen
Seventeen projects in this region, between 2030 and 2033, that received a date from me and then stopped existing. I know because I terminated the agreements at the customers' request, and because I watched the companies go.
Six of them needed no reinforcement at all when assessed on their own. Six projects that my network could have accepted with a bay and a few weeks, which were handed dates generated by a background of contracted capacity, and which did not survive the wait.
I have their names. I have, in four cases, the email in which somebody who had spent two years of their life on it told me they were stopping. I am not going to reproduce those.
The cost nobody computes
There is no document anywhere — not in my company, not at the system operator, not at the regulator — which holds the number projects killed by a date produced by capacity that does not exist.
The reason is instructive. To compute it you would have to form a view about which contracted capacity is real, and forming that view is the thing nobody is permitted to do. The measurement is prohibited by the same rule that creates the problem, which is as neat a trap as I have encountered in fourteen years of a career made largely of traps.
So the queue's cost is distributed into three places where nobody adds it up: constraint payments, which are a system operator line; reinforcement apportionment, which is a charging matter; and abandoned projects, which are commercial decisions by private companies and therefore nobody's statistic at all.
Each of those three is somebody's number. The sum of them is nobody's number. And a cost that is nobody's number does not have to compete with anything, which is why it has been growing for a decade while everybody involved has been doing their job properly.