Chapter FifteenStill True

Chapter 15 of 183 min read596 words

WHAT I AM ASKING FOR That a queue position be re-evidenced to be retained. Every two years, the holder of a connection agreement re-submits the same evidence their own application asserted: the land right they claimed, the planning status they claimed, the capacity they applied for. Not a new test. The same claims, still true. Failure to re-evidence within 90 days releases the position, and the released capacity is reoffered in queue order to those behind it. The company forms no view on the quality, likelihood or merit of any project. It checks only that what the applicant said is still what the applicant says.

I am not asking to be allowed to judge projects. I am asking that the burden of showing a project is real sit with the project.

โ–

Why this is different from milestones

Milestones ask: are you making progress? That is a question about effort, it requires somebody to assess whether effort is reasonable, and it is satisfied by five thousand pounds of correspondence. I showed you what comes back.

Re-evidencing asks: is the thing you told us still true? That is a question with a documentary answer. You said on 14 March 2030 that you held an option over this land. Produce it, or produce its replacement, or say that you do not.

There is no judgement in that and that is the entire design. I do not decide whether your option is good enough, whether your consent is likely, whether your project is wise. I check whether the statement in your application is still a statement you are willing to make. If it is, your position is untouched, whatever I privately think of it โ€” and I will go on thinking things and go on being unable to act on them, which is correct.

โ–

What it would have done at Calderbeck

Of my seventy-one: the nine with lapsed or sold land rights could not re-evidence, because the claim is simply no longer true. The 240 MW at Fernlow Rise could not re-evidence, because the site has sixty-two houses on it.

The fifty-eight with no planning application would mostly survive, because most of them never claimed a planning application โ€” they claimed a site and an intention, and an intention is still an intention. I want to be honest that my own headline number does not clear. I would guess the rule releases somewhere between one and two gigawatts of the eight point six, and anybody who promises you more than that is selling the same optimism I have spent a book complaining about.

One to two gigawatts at that boundary is not enough to remove the 400 kV circuit. It is enough that a 49.9 MW battery at an existing substation with a spare bay would have been studied against a background with room in it.

โ–

Why I think it is small

It asks for no new information. Every document re-submitted was already asserted by the applicant, in writing, in their own application. There is no new duty, no new disclosure, no commercially sensitive material leaving anybody's hands, and nothing for a monopoly to form an opinion about.

It is a letter every two years saying still true, and a consequence for not sending it.

The expensive part is not the check; it is the release. A release re-studies everything behind it, which is real work, and I am asking for work. I would rather ask for work than for discretion, because work I can be held to and discretion I cannot be trusted with.