POSSESSION RECORD โ SEM/142 NETHERFOLD Possession taken: Friday 19 November 2032, 23:40. Possession given up: Monday 22 November 2032, 03:55. Duration 52 hours 15 minutes. Work: replace bearing SEM/142/B3; clean and re-pack bearing shelf; replace shelf drainage; renew bearing SEM/142/B4 as precaution (same batch, same exposure). Jacking operations: 6 hours 20 minutes. Bearing removal and installation: 9 hours 05 minutes. Total time with the deck actually lifted and the bearing out: under sixteen hours. Restriction removed, line open at line speed: Monday 22 November 2032, 04:10.
Fifty-two hours and fifteen minutes. Five hundred and sixty-six days of restriction to buy fifty-two hours of access.
What it was like
I was there for the whole possession, which is not required and not usual for a structures engineer at my grade, and which I will not pretend was about anything other than wanting to see it end.
Cold, loud, floodlit, and completely routine. The jacking contractor had done forty of these. The bearing came out at eleven minutes past four on the Sunday morning, after an hour of persuasion with a hydraulic wedge, and it came out in one piece.
There is a photograph on my phone of the old bearing on a pallet, with a chalk mark on the housing where the corrosion had bridged the sliding surface and welded steel to steel. The failure was perhaps the size of my hand.
I had the photograph taken because I wanted a record of the scale of the thing. The size of my hand, and five hundred and sixty-six days, and eleven point nine million pounds.
What the delay inside the possession was
The works were programmed to need fifty-one of the fifty-two and a quarter hours available, and finished with two hours in hand, which the delivery report records as a success, and it was one.
Of the fifty-two hours, the actual structural operation โ deck lifted, old bearing out, new bearing in, deck down โ took under sixteen. The rest was isolation of the overhead line, access, setting up and demobilising, protection, and the drainage work, all of which has to happen and none of which could be shortened much.
Nobody involved in the repair was slow. Every hour of the fifty-two was being used by somebody competent. The whole of the waste at Netherfold happened in the eighteen months when nothing was being done at all, by people who were also not slow, who were working to the only schedule the railway has.
The thing Hartnoll said at the end
He came out on the Sunday night, which he did not have to do either.
He watched the second bearing go in and said: "That's it? That's the whole thing?"
And I said yes, that is the whole thing, and he stood there for a while and then said: "We should have found you a weekend."
There had been a weekend. There had been seventy-eight of them between the assessment and the possession, every one of them allocated to work that somebody else needed as much as I needed this โ and the reason mine did not win any of them is not that the railway is badly run. It is that when I was asked what the consequence of waiting would be, I wrote four words, and four words do not beat a track renewal.