ENERGY CENTRE DESIGN BASIS โ THORNMERE RIVERSIDE, 2020 Design connected load: 1,420 dwellings (4 phases), 1 primary school, 1 leisure centre. Peak heat demand: 8.9 MW (with diversity). Annual heat delivery: 17,400 MWh. Plant: 2 ร 2.4 MW gas CHP; 8 MW gas standby boilers; 180 mยณ thermal store. Distribution: 1,900 m of pre-insulated primary mains, DN250 reducing to DN100, buried to 1.1 m. Capital cost: ยฃ14.8m, funded by a 25-year senior loan at 4.1%. Design life of buried mains: 40 years. Plant: 20 years with overhaul at 10.
Nineteen hundred metres of pipe in the ground, eight point nine megawatts of plant, fourteen point eight million pounds of capital, all of it correct for fourteen hundred and twenty homes.
Why a network is built for the final phase
You cannot build a third of a buried main.
The primary route runs from the energy centre at the north of the site, under the access road, through the park, past the school and down to where phases three and four were to be. Its diameter is set by the flow it must one day carry; you cannot lay a DN100 and enlarge it in 2029 without digging up the road, the park and the school apron a second time, at a cost greater than laying DN250 once.
The same is true, with qualifications, of the energy centre: the building, the flues, the thermal store and the electrical connection are sized for the whole scheme, because retrofitting a plant room is brutal and because the planning permission for the building was granted once.
Sequential build-out of infrastructure is more expensive than building it right the first time, and the engineering decision to build it once, for the consented scheme, is the correct engineering decision. I have checked it twice, hoping to find waste. There is none.
What the loan assumed
A twenty-five-year senior loan of fourteen point eight million pounds, drawn in 2020, service of six hundred and forty thousand pounds a year, underwritten against a cash flow with fourteen hundred and twenty connections phased from 2021 to 2028.
The lender did the obvious thing and tested that cash flow against downside cases: slower sales, higher gas prices, a phase delayed by two years. What the lender did not test, and what I have never seen tested on any scheme, is a case in which half the development does not get built at all, because a consented residential phase on a riverside site in that market was, in 2020, about as close to certain as a thing can be.
They were wrong, and so would I have been, and so was everybody.
The two costs that do not scale
Debt service. Six hundred and forty thousand pounds a year, fixed, until 2045, on an asset two thirds of which is doing nothing.
Maintenance of the buried network. The mains are there. They must be pressurised, monitored, inspected and insured over their full length, because a dead leg of DN200 primary still fails, still floods, and is still my company's asset under the highway.
Four hundred and ten thousand pounds a year of operation and maintenance, of which I can attribute perhaps a hundred and forty thousand to the part of the network actually delivering heat.
The rest is the cost of owning pipe that leads to a field.